Thursday, April 30, 2020

Turkey Creek Ph -1 Flat Creek (Line Work)


7:20am- crew back to lay pipe today as waters have receded. 

8:30am- joint #1 in being placed. 

9:45am- joint 2 now in place. Pump at MH A25 had to be readjusted. Hose was in to much silt. 

10:35am- crew has hit rock and will need trackhoe and hammer of which are here at the top. Crew picking up barrel section for MH A26 while here. 

11:30am- breaking rock now. 

12:30pm- still breaking rock...

2:15pm- 4th joint now in and grading out for fifth.  

2:30pm- 5th now placed. 

3:15pm- joint 6 now in place. 

4:25pm- 7th joint now laid in place and will be the final one for today. Ditch will be backfilled to round out the day. 