7:30am- crew is setting laser back up to see were they are at.
Dot is still below target...
8:35am- crew will be digging up the 3 joints laid yesterday and and relaying them today. Pump is getting moved first though.
10:45am- The last 3 joints have been removed and two of those are now laid back to grade.
11:30am- 3rd joint dug up now back to grade.
12:25pm- RR03 bore has almost another 20’ in bring total to nearly 80’ thus far.
1:15pm- Pipe crew has now laid their 1st & 2nd joints for the day so far.
2:20pm- 3rd joint for today now in place.
Backfill is continuous at this point.
3:20pm- still at 3 joints as crew has been benching down and moving material so they have more room.
4:40pm- 4th joint now in for today.
5:00pm- backfill will make up rest of the day. 56’ of 27” sdr35 for today.