Tuesday, April 14, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:30am- crew is setting laser back up to see were they are at. 

Dot is still below target...

8:35am- crew will be digging up the 3 joints laid yesterday and and relaying them today. Pump is getting moved first though. 

10:45am- The last 3 joints have been removed and two of those are now laid back to grade. 

11:30am- 3rd joint dug up now back to grade. 

12:25pm- RR03 bore has almost another 20’ in bring total to nearly 80’ thus far. 

1:15pm- Pipe crew has now laid their 1st & 2nd joints for the day so far. 

2:20pm- 3rd joint for today now in place. 

Backfill is continuous at this point. 

3:20pm- still at 3 joints as crew has been benching down and moving material so they have more room. 

4:40pm- 4th joint now in for today. 

5:00pm- backfill will make up rest of the day. 56’ of 27” sdr35 for today. 