7:20am- crew is pumping water. More line to be laid today.
8:30am- 2nd joint so far this morning has gone in.
9:40am- 4th joint now in.
10:40am- breaking rock now.
11:25am- joint #5 going in.
12:10pm- RR03 has now achieved about 10’ of casing in the ground now.
1:30pm- breaking rock. Dig excavator broke a hose. Still at 5 joints of pipe so far.
2:40pm- 6th joint now in. Excavator has been fixed.
4:10pm- crew says no more pipe will be laid today. Water pump has now broke a hose that will need repair. 84’ of 27” sdr35 today.
5:20pm- RR03 bore crew now has 15’ of casing in.