7:15am- Bring Contractor will be pumping water for a while this morning. Crew has 60’ of casing now in and will be welding on next section once water is gone.
8:05am- Line crew is pumping water and will begin with rock breaking.
10:05am- 1st joint has f the day now placed.
11:50am- 2nd joint now in. I’m headed now to WWTF for concrete pour.
2:50pm- 3rd joint has been laid, but there is another laser issue. As the target NOW indicates, the pipe is laid high...with fear that other joints have been laid high as well. They are currently indecisive on what to do.
3:30pm- So, calls have been made to Ozark Laser and Chris has stated that they think its due to the air moving through the pipe. Crew will now stack out MH A23 to see if that helps.
4:55pm- crew now has all manholes covered to a point. Dot improved, but isn't quite there yet. They will recheck in the morning.
5:20pm- Boring crew did not bore any today. They spent their day so far pumping water and getting the next piece of casing welded on. They will work until 7pm tonight.