6:55am- forms are now completely stripped and bituminous coating is almost done.
9:20am- hole is getting drilled into valve vault for 2” drain line from meter pit. The line was forgot when walls were poured.
1:50pm- crew tapping gravel to get to grade of floor elevation of stem walls where generator will set.
Issue though of not having the ductile pipe wrapped. Crew will dig back around pipe and wrap it now.
2:15pm- pipe is now wrapped and crew is back to tamping clean rock.
5:45pm- grade is achieved for floor that will be footings also for gen pad.
Forms going up; pour for floor will happen around 9am tomorrow. Called James to have more cylinders brought to me for the future pours.