Tuesday, April 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:25am- crew bedding for 1st joint to be laid. 

7:30am- Placing joint #1 for the day. 

8:20am- joint #2 now going in place. 

9:00am- Breaking rock for 3rd joint. 

More backfill occurs. 

9:50am-3rd joint getting graveled up. 

10:35am- 4th joint now that n. 

11:15am- crew has had a mishap...last joint laid was high and they tried to pull it out to redo it and two joints came instead of the one. 



Gravel removal now occurring. 

11:40am- the resetting of joint 3 now done as gravel goes back over pipe. 

12:05pm- joint 4 now back in place. 

1:20pm- Joint 5 makes its way to the ditch finally.

2:00pm- 6th joint now laid. Had some issues with laser, but crew has a fan running pulling air through pipe now. 

2:40pm- joint #7 now going in. 

4:15pm- joint 8 makes its way to the ditch after more laser issues. 

4:25pm- with about 120’ of ditch to back fill the crew has stopped laying pipe for the day. 8 joints or 112’ of 27” laid today. 