7:25am- crew bedding for 1st joint to be laid.
7:30am- Placing joint #1 for the day.
8:20am- joint #2 now going in place.
9:00am- Breaking rock for 3rd joint.
More backfill occurs.
9:50am-3rd joint getting graveled up.
10:35am- 4th joint now that n.
11:15am- crew has had a mishap...last joint laid was high and they tried to pull it out to redo it and two joints came instead of the one.
Gravel removal now occurring.
11:40am- the resetting of joint 3 now done as gravel goes back over pipe.
12:05pm- joint 4 now back in place.
1:20pm- Joint 5 makes its way to the ditch finally.
2:00pm- 6th joint now laid. Had some issues with laser, but crew has a fan running pulling air through pipe now.
2:40pm- joint #7 now going in.
4:15pm- joint 8 makes its way to the ditch after more laser issues.
4:25pm- with about 120’ of ditch to back fill the crew has stopped laying pipe for the day. 8 joints or 112’ of 27” laid today.
No comments:
Post a Comment