Tuesday, April 7, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:45am- onsite at RR03 bore on Laytons. Tracks are being shot, Rail Pros are onsite, and grade is getting rechecked by Iowa Trenchless, with Flat Creek present(Kenny &Chris) to witness. Casing is 4 hundredths high. Everyone is ok with this. 



8:40am- discharge pits are dug for the pumping of water on the west side of bore and additional work is being done on east side to prevent sediment entering into creek. 



8:50am- crew is getting ready to weld head onto casing to begin turning. 

10:00am- 3rd pipe is in the ditch now. I have asked them to remove the mud chunks in the gravel around the pipe. 



11:24am- 5th pipe now laid and covered with gravel. 

11:45am- 6” pump is moved and pipe is graveled up. 

12:00pm- pipe is covered with material and detection tape placed as dozer makes roadway back over pipe. 

1:20pm- Laytons property now has some silt checks installed. 



1:30pm- crew is just about ready to begin bore, but first some final checks. 

2:20pm- cutter is now fully engaged into the concrete. Boring begins. 

3:05pm- 7joints are now laid for today on Rittenhouse. 

4:00pm- 9 joints now in so far. 

4:30pm- 10th joint for today as crew will now move pump and bed pipe where hose has been. 

4:45pm- pump now getting moved. 

4:55pm- gravel getting placed around pipe. 

5:05pm- backfill begins. 