Friday, April 3, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- water is pumped down, backfill looks like it went well and still going. Crew to lay pipe and set MH A23 today. 

8:25am- 1st piece of pipe now being placed. 

10:20am- MH A23 is now set and connected to line. 21’-6” of 27” sdr35 is laid up to MH A23. 

Line is lamped by laser back to MH A22. 

12:05pm- 1st joint now laid upstream of MH A23. 

1:20pm- 2nd now laid upstream of MH A23. 

2:05pm- 3rd now laid upstream of manhole A23. 

2:35pm- 4th now in place this side of A23. 

3:14pm- 5-1/2 joints (77’) are laid today total and manhole A23 is set. 
Gravel is place just before manhole A23 to cover pipe and crew will spend rest of their day backfilling and moving the pump to end of pipe. 