Both crews are back today. Walls for generator area to be set and dirt will start going back in around lift station.
9:00am- manhole A1 is stacked out now as dirt is beginning to be placed.
Rebar getting tied and forms going in next. Pour around 1:00pm today.
12:35pm- inner forms are up as outter forms will be next on generator walls. Pour now pushed back to 2:30pm.
More fill still going in.
3:00pm- pour is going fine. Concrete was tested with the following results; Air: 6.25%, Slump: 4”, Temp: 60*F. 4 cylinders are made.