7:00am- Crew onsite today to work through rain and lay some pipe.
8:05am- crew has the 4” pump now running here at the end of the pipe.
8:24am- 1st joint laid. More gravel to be applied.
9:25am- 2nd joint now in place.
9:55am- 3rd joint in and backfill is occurring.
10:40am- 4th joint now going in. Excavator had to be traded out due to a blown hose. 490 now being used.
11:45am- 5th joint now in place.
12:40pm- joint #6 is in and crew will call it a day as rain begins again. Backfill will occur up to end of line.