Friday, April 10, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- At RR03 site for a meeting with the contractor and Property Owner. 
Boring contractor appears to be doing good. Looks like another 10’ of casing is in, which brings the total footage to 30 now. 

9:45am- another 5’ of casing is now in. Meeting with the Property owner went well. 

I’m headed offsite. 