7:05 am- water is pumped down already this AM. Crew will be setting laser up to begin laying pipe today.
7:35am- 1st joint now in place for today.
8:25am- 2nd pipe now in. I will be headed to the WWTF for a concrete pour.
9:05am- 3rd stick now placed.
10:10am- 4th now in place and all graveled up.
10:45am- 5th joint now placed. All seems to be going ok today so far!
11:15am- 6th piece in.
12:00pm- 7th joint now placed. I have continually spoke with Chris about the importance of having the gravel “level” across the ditch line.
1:30pm- 8th joint now laid.
2:00pm- #9 now laid.
2:50pm- 10th joint now laid.
A look into the pipe.
3:35pm- 11th piece now laid.
4:20pm- 12th joint of pipe now laid in place. Crew will round out the day with backfilling.