Tuesday, April 21, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- crew will continue to lay pipe today from MH A25 towards A26 location. 

7:55am- 1st joint of the day going in. 

9:05am- 3rd joint going in. 

10:15am- 5th joint now being placed. 

11:30am- 7th joint now in place. 

12:30pm- 8th joint in. 

1:10pm- 9th joint now placed. 

2:10pm- #10 now laid. 

3:00pm- joint 11 now in place. 

3:50pm- Bore RR04 is now receiving carrier pipe. 

4:25pm- still going in. 

5:04pm-  12” sewer pipe now installed in casing at RR04. 
East side. 

West side. 

5:10pm- 15 joints of pipe were laid today for 210’ of 27” sdr35. 