6:40am- crew will tie rebar and then pour top pad for generator.
1:10pm- concrete has finally arrived. Testing was done with the following results; Air: 8%, Slump: 5”, Temp: 64*F. Warm water was used due to temperature today. Four cylinders were also made for testing today.
At future stairway base.
5:35pm- Crew worked to remove interior ceiling supports out of wet well this afternoon.
Also I met with Electrician and Liberty Electric to go over meter location and such and to understand what they were requesting from Dale that wasn't in the plans and specs. Come to find out, nothing other than the height of the bottom of the boxes needed to be above the Flood plain and that there needed to be a work area in front of the boxes that aligned with their requirements as seen below.