8:00am- crew has another pump onsite now and will be getting it in place to begin pumping water.
9:25am- no pipe laid yet for today. Water is done and gravel placed for first joint, but more rock breaking has to occur. A joint wont fit due to not enough rock brock out yet.
10:20am- 1st joint of pipe now going in.
11:10am- more rock breaking occurring.
12:15pm- a 20’ casing is welded on and crew will begin again after the blasting that is too occur.
12:20pm- Blast now completed.
1:22pm- 2nd joint in as more tock breaking occurs.
1:50pm- 3rd joint now placed.
3:20pm- 4th joint now in place.
4:10pm- no more pipe is laid. Pump was moved after hole was broke out at the end of the pipe.
4:55pm- tarps are finally onsite and are going over the stored pipe at Access Rd #3.