Wednesday, April 8, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


6:50am- crew is laying ductile this morning and continuing to backfill around the liftstation. 



12:40pm- ductile line is now complete from liftstation to headworks of plant. 

Also, pump by-pass connection is done. 

Stub outs for electric for generator also completed today. 

Crew will continue to backfill trench and lift station for the remainder of today. 

4:40pm- things are shaping up rather nicely here. Dirt is going in good and things are coming together. 