7:10am- water is pumped down at this time and crew will begin laying pipe on towards MH A26.
8:00am- some hoses have been changed out on the 360 excavator and it will now be back in use today.
8:45am- 1st joint of the day!
9:20am- 2nd joint going in.
9:45am- 3rd going in.
10:25am- 4th joint.
10:50am- ditch caves in on 5th joint setting... will now be pulled out.
11:05am- 5th joint now in place.
11:35am- 6th joint now in place.
12:05pm- 7th joint getting placed.
12:55am- rock is being broke out as backfill begins.
1:40pm- 8th joint going in now.
2:40pm- still breaking rock for the 9th joint...
3:20pm- 9th joint going in.
4:00pm- joint 10 now going in.
5:00pm- crew is calling it a day as more backfilling occurs. Also starting to rain now. 10 joints for todays total.