Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- water is pumped down at this time and crew will begin laying pipe on towards MH A26. 

8:00am- some hoses have been changed out on the 360 excavator and it will now be back in use today. 

8:45am- 1st joint of the day!

9:20am- 2nd joint going in. 

9:45am- 3rd going in. 

10:25am- 4th joint. 

10:50am- ditch caves in on 5th joint setting... will now be pulled out. 

11:05am- 5th joint now in place. 

11:35am- 6th joint now in place. 

12:05pm- 7th joint getting placed. 

12:55am- rock is being broke out as backfill begins. 

1:40pm- 8th joint going in now. 

2:40pm- still breaking rock for the 9th joint...

3:20pm- 9th joint going in. 

4:00pm- joint 10 now going in. 

5:00pm- crew is calling it a day as more backfilling occurs. Also starting to rain now. 10 joints for todays total.  







 