7:15am- Pipe crew are fueling equipment before getting started with moving to East side of creek to MH A25 location and beginning the day digging.
8:10am- Hole for MH A25 is being dug and water is present right away.
9:40am- still trying to get water down at MH A25 location.
11:00am- still pumping water at this time. Crew is moving dirt and rock from north end of job to access 3 area where it enters field.
12:30pm- 90’ of casing is in, but crew has pulled augers and are in the process of steering it a bit. They are confident though that they will hit their target on the other side.
1:30pm- rock material is now being hauled to access road 3 and is getting placed in areas of constant maintenance.
2:40pm- Placing rock.
4:10pm- more rock going down.
5:10pm- 100’ now in at RR03.
5:30pm- crew has unhooked from the augers and will begin to get the last casing in the pit yet today and begin welding it up.