Friday, May 1, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:30am- equipment has all been fueled now and crew measures out for sitting of MH A26 today. 

8:35am- almost dug out for MH A26. 

9:40am- 1st joint and moving dirt still to be able to set base of A26. 

10:00am- placing and leveling gravel now for manhole. 

10:40am- MH A26 base is now set with and additional 8.5’ of pipe on into the manhole for a total of 22.5’ of 27” laid today. 

10:50am- Line is lamped all the way back to Mh A25. 
Essentially a 904’ run!

A closer look...😁

11:55am- gravel now placed on pipes and joint sealer is getting placed. Straps to follow. 

1:15pm- laser has been put in 12” pipe at Bore #4 and grade is .565. They will prep everything and get ready to set MH A27 on Monday. 



1:40pm- backfill and more straps are placed on and around MH A26. Crew will be leaving at 2:00pm today due to them being on overtime at that point. 