7:32am- Today seems to be moving much smoother than yesterday. Setting pipe in place first thing.
9:34am- Fourth stick so far for the day. Continue to excavate.
10:40am- Setting the 6th piece of sewer pipe for the day
1:01pm- 8th piece of pipe in for the day, continue to excavate
2:00pm- Pipe # 9 for the day, Moving right along
2:30pm- Breaking Rock
4:03pm- Placed the 11th piece of pipe for the day
5:09pm- Last piece of pipe set for the day # 12