Thursday, May 21, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:05am- crew will continue with pipe laying on to MH A11 location. 

8:30am- 1st of the day!

9:25am- joint #2 now laid. 

10:10am- rock is encountered and has to be broke out.

10:45am- 3rd joint now laid. 

12:00pm- 4th joint now in. 

1:20pm- more rock to be broke. Bore pit is getting filled in as they dig so that manhole can be set later. 


2:00pm- 5th joint in as bore pit continues to be filled. 

2:25pm- 6th piece of pipe now in place. 



3:20pm- back in rock at edge of bore pit. 

4:30pm- 7th joint now going in. 

4:45pm- jack hammer going back on to end the day here. Crew is now essentially at MH A11 location. 


-Long weekend so crew wont be back until next Tuesday. 