Crew will lay pipe today with hopes of getting to MH A10.
7:30am- Pumping water at this point...
4” pump is not sucking this morning for some reason.
7:50am- 4” pump is back working now.
8:45am- 1st joint in with gravel to follow.
9:15am- Jack hammer in use now...
9:55am- 2nd joint going in.
10:24am- 3rd joint going in.
10:55am- 4th now laid.
11:35am- 5th joint now being placed.
12:45pm- joint #6 now being laid.
1:55pm- 7th now placed. Crew had a laser issue, but has it fixed now.
2:24pm- #8 now in place.
3:05pm- joint 9 now getting gravel.
3:35pm- digging out to set MH A10.
5:30pm- MH A10 Base is set and connected to the pipe with another 19.66’ of 27” making todays total 145.66’ of 27” PS46.
Line is also lamped by laser back to MH A9.