7:05am- crew onsite to lay more pipe today. Water is up in the creek, but pump seems to be keeping up with it in the ditch at this point.
7:40am- still a lot of water coming through the pipe... crew is hoping that it will slow down here shortly...to much to set laser.
8:35am- joint #1 being graveled.
9:00am- 2nd joint of pipe now going in. Crew will have to set another pump up at end of pipe due to increased water Infiltration.
9:35am- 4” pump now set up.
10:20am- crew still trying to get water pumped down. Rock has been broken out with jack hammer and hose repositioned.
10:50am- 3rd joint now in place.
11:20am- crew is going to swap pumps around and bring 6” to this end. 4” cant keep up.
12:40pm- 4th joint now being laid.
1:20pm- 5th joint now getting gravel.
2:10pm- 6th joint now placed.
2:45pm- 7th joint in, but bank has collapsed.
3:25pm- 8th piece of pipe now laid. More gravel to be applied.
4:35pm- Joint 10 now going in.
5:05 pm- crew is calling it a day. 10 joints @ 140’.