Wednesday, May 6, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew will be working on going back getting rest of the manholes wrapped and strapped today. They will walk in and start at MH A26 to finish it then move to 25. I’m going back around to drive in once roadway is smoothed back up. 

7:45am- crew at MH A26 with the wrap and straps done. Lid is dry set due to line E connection. 



8:20am- plug going in at MH A25. 

Wrapped and strapped now except for top. 

9:55am- more backfill and cleanup before moving down to next manhole. 

10:40am- 6” pump now moved to MH A23 location. Water will be pumped down so this one can be wrapped and strapped. 

11:50am- crew will begin hauling down manholes and pipe the rest of the way today while waiting on the water to pump down. They will go from MH A20 downstream with the materials. 

12:55pm- Materials are getting spread out on Laytons property. 

Area cleared all the way to Bore 2 location. 

Looking back upstream of bore 2. 

Bore 3 location looking upstream. 

1st creek crossing upstream of bore 3. 

At 2nd stream crossing looking upstream. 

A view back downstream from here. 

And looking back across stream crossing 2 downstream. 

At stream crossing 3 from Bore 3 upstream. 
Looking across to Rittenhouse property. 

And a view from here back downstream across Laytons property. 

1:45pm- manholes will be delivered across creek for this section of Laytons property between stream crossing 3 and 2. 

3:40pm- MH A17 now being delivered. 

3:50pm- Just witnessed a failure of the swivel hook!



The nut had worn the threads almost smooth!



4:45pm- crew has ordered a new #17 manhole, and Im now headed offsite.