7:00am- Creek was up over the weekend. 4” pump got under water and 6” pump is still pumping water this morning.
7:30am- 4” pump is getting set back up and will attempt to start it.
8:30am- 4” & 3” gas pumps are not working as well this morning. All the water has played havoc on them.
Crew will continue to work on them until one or all are back running.
9:00am- The two gas powered pumps are now running and pumping water at this time. The 4” diesel pump still having issues.
10:20am- crew have now shot grade on the “out”side of MH A10 for a quick check. It has shot about 2 hundredths low. They will begin alignment to MH A11.
10:45am- alignment to MH A11 now complete.
11:55am- 1st joint of the day going in.
1:20pm- 2nd joint now in place.
1:50pm- 3rd now getting placed.
2:30pm- 4th now laid.
3:10pm- 5th joint now getting placed.
3:40pm- joint #6 now going in.
4:20pm- 7th joint now placed.
5:00pm- 8th joint now in place. Backfilling also commencing.
5:15pm- crew is calling it a day.