Thursday, May 7, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- crew will unload manholes when they arrive first thing this morning. MH A27 and E1 is coming. 

7:10am- part of the crew is at A27 site and has water pumped down and awaiting manhole. 

Cleanup over swamp area. 

8:24am- MH A27 has arrived to the site. 

9:45am- gravel now going in for manhole base. Lasers are set up in each pipe for proper alignment manhole. 

10:10am- Tracer wire is now through Bore 4. 

11:15am- MH A27 now set and pipes connected. 39’ of 12” sdr35 laid today and manhole A 27 set. 

Line is also lamped from MH A27 back to A26. 

12:00pm- MH A27 is dry stacked due to the barrel section having cracks. Crew will bring another over to replace it at some point. 

1:30pm- crew has made it back to MH A23 and are in the process of wrapping and strapping it. Lid will also be changed out shortly. 

2:50pm- MH A23 is now wrapped and strapped. All lids will still need replaced and bolted down. 

3:15pm- Area between manholes A21 and 23 starting to come together. Dirt is being pushed so that it can start to dry out. 



4:00pm- crew will more equipment around and haul some pipe to finish out the day. I will be headed offsite. 