Tuesday, May 26, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- crew has pumps running to evacuate the water from the bore pit and trench. Iowa Trenchless may not be here this week due to rain forecasted. 





9:14am- still pumping water...



10:35am- breaking rock at MH A11 location roughly. 

11:25am- 1st joint of the day going in. 

12:45pm- Blasting occurs at this time. 

12:50pm- crew setting laser in bore pipe for alignment of MH A11.

1:45pm- crew is double checking manhole elevations. 



2:50pm- crew has now connected MH A11 to the downstream pipe with a total of  25.33’ of 27” PS46 for the day. 
Gravel now going in to properly bed the pipe. 





Line is also lamped by laser back to MH A10. 

4:15pm- MH A11 is stacked out now and wrap is going on bottom seam. 

4:50pm- straps are now on bottom seam. Crew will be picking up to call it a day. 