7:15am- crew has pumps running to evacuate the water from the bore pit and trench. Iowa Trenchless may not be here this week due to rain forecasted.
9:14am- still pumping water...
10:35am- breaking rock at MH A11 location roughly.
11:25am- 1st joint of the day going in.
12:45pm- Blasting occurs at this time.
12:50pm- crew setting laser in bore pipe for alignment of MH A11.
1:45pm- crew is double checking manhole elevations.
2:50pm- crew has now connected MH A11 to the downstream pipe with a total of 25.33’ of 27” PS46 for the day.
Gravel now going in to properly bed the pipe.
Line is also lamped by laser back to MH A10.
4:15pm- MH A11 is stacked out now and wrap is going on bottom seam.
4:50pm- straps are now on bottom seam. Crew will be picking up to call it a day.