Tuesday, May 5, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


More 12” line to be laid from MH A26 area upstream. 
7:20am- crew aligning laser dot this morning. 

Equipment is also being worked on. Dozer arm popped off yesterday. 

8:05am- 1st joint of the day in and second is going in. 

8:45am- 4th joint of the day now in place. 

9:35am- 7th joint now laid. Jimmy’s son Isaiah is learning today.

10:25am- 11th joint now being placed. 

11:15am- joint 13 now in as rock now needs broke out. 

11:50am- Drilling is getting down at Bore 1 on WWTF side for relief holes as they will begin breaking rock here on Monday. 

1:15pm- 17 joints laid now on the 12”. 

1:45pm- breaking rock...

2:40pm- joint #18 has been laid and #19 going in. 

3:30pm- ditch is dug to MH A27 location now as crew breaks rock for last joint to be laid today #20. 

4:20pm- Joint 20 is laid. 280’ of 12” sdr35 today. 
Crew will dig circumference out for MH A27 now. 

4:40pm- area for manhole 27 is dug, rock placed in front of pipe and backfill will resume for the rest of the day. 