6:55am- Crew will continue with laying pipe today and should get to MH A11 location today.
8:05am- pumps had to be switched around this morning due to a belt being broke on the 6” pump again...the 4” pump is now at the end of pipe.
9:00am- First pipe of the day going in at this time.
10:00am- 4” pumping having trouble keeping up I believe...still on first joint of the day.
10:30am- Spencer and Brad onsite to look at stream bank stabilization today.
1:40pm- crew has now laid 3 joints of pipe today with having to break some rock to get them installed. 4” pump will also get moved up.
1:40pm- crew has now laid 3 joints of pipe today with having to break some rock to get them installed. 4” pump will also get moved up.
2:30pm- 4th pipe now placed for the day.
3:35pm- joints 5&6 are now laid. Ditch has narrowed up due to the rock being more stable on the sides on the banks.
4:30pm- 7th and final joint is laid today. Crew will backfill to finish out their day.