Thursday, July 30, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:40am- Iowa has pulled casing back some and will attempt again to get casing down some. They are currently running at 1% instead of the required .5%. 
No headway was made yesterday due to equipment issues. 

Crew making repairs this morning to bore machine. 

7:30am- crew will begin again today with trying to get MH A25 tied to bore. 

8:45am- 2nd joint going in now. 

9:40am- 4th joint before gravel. 

11:20am- more rock is being broke on up to manhole. Still 4 joints placed without gravel on top so that piping can be connected to manhole once there. 

11:55am- MH A24 getting wrapped and strapped on top now. 

Also 2 joints of pipe were taken back out due to the amount of water coming into ditch. 

12:55pm- Rip Rap bank stabilization area is marked out on MH A24 side. 

1:15pm- keyway is dug down to solid rock and rip rap is now being placed. 

2:25pm- cap is pulled loose from MH A25, but now the crew is chasing the laser downstream due to the gush of water going into the pipe. 

3:20pm- laser is located down at MH A23. Crew continues now with digging out at MH A25. 

A look back at MH A24 side where a bit of rip rap has been placed. 

4:05pm- 3joints total have now been removed from ditch that were laid today and gravel is getting regraded so that pipe can be relaid on up to and connect into MH A25. 

5:05pm- crew is calling it a day. After setting laser back up and installing two pipes back in ditch, the grade is off by 4”. Something is wrong. Crew will tear pipe back out Monday. 

5:25pm- Iowa appears to have rest of the 2nd piece of casing in now, but no one is onsite for me to ask foresure. I’ll check back on the job on Monday. 