7:30am- The creek bore at MH A16-17 now has casing. Grades will be shot this morning and casing adjustments will be done.
8:30am- Gravel is placed and casing is raised to top of hole. .275% by laser is grade across flow line of casing now.
- progress meeting at TCRSD
11:40am- crew had laid 4 joints of pipe so far today and has half of the rebar cage installed for the next section of encasement.
11:40am- crew had laid 4 joints of pipe so far today and has half of the rebar cage installed for the next section of encasement.
12:50pm- 5 joints laid and the top half of the encasement is in place.
1:40pm- 20’ of concrete encasement now completed at approximate STA 28+20 - 28+40.
2:00pm- no more pipe will be laid today. Crew will move spoil materials from areas of cleanup so more topsoil can be spread out.