7:00am- the plug the crew installed yesterday to hold water back from L.S. leaked last night so they are now pumping out again. Ditches for electrical are getting dug also.
Dirt pad partially built now in front of rack.
3:00pm- materials are now sitting in L.S. for installation yet to come. Electrician is still running conduits and getting some wires pulled. Conduits are shallow and I have asked that they be lowered as much as possible so that they sit well below finished grade.
4:25pm- conduits are now lowered.
Ground wires are welded together.
I have spent sometime talking with Mike about how they want to go about cleanup and such; I have also talked with Chris about his schedule and trying to coordinate things.
There is probably going to be some disagreements between the two, but I will continue to try and mediate the situation.