Bore pit at the WWTF is coming along and should be nearing completion.
7:45am- crew tying rebar for concrete encasement that will be installed today at STA 27+00 - 27+30.
10:15am- 1st joint of the day in and this will be the beginning of the encasement for 30’.
11:30am- 2nd joint in and part of the rebar is in place.
1:40pm- rebar cage is in and tied. Concrete should arrive here shortly.
2:40pm- encasement almost complete.
3:10pm- concrete now in place and encasement is completed. Gravel going around the rest of the 4th joint of the day.
4:00pm- joints 5&6 now placed.
4:25pm- joint 7 is in and backfill will now have ccur to finish the day here.