Monday, July 13, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Bore pit at the WWTF  is coming along and should be nearing completion. 

7:45am- crew tying rebar for concrete encasement that will be installed today at STA 27+00 - 27+30. 

10:15am- 1st joint of the day in and this will be the beginning of the encasement for 30’. 

11:30am- 2nd joint in and part of the rebar is in place. 

1:40pm- rebar cage is in and tied. Concrete should arrive here shortly. 

2:40pm- encasement almost complete. 

3:10pm- concrete now in place and encasement is completed. Gravel going around the rest of the 4th joint of the day. 

4:00pm- joints 5&6 now placed. 

4:25pm- joint 7 is in and backfill will now have ccur to finish the day here. 