Monday, July 27, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- Iowa has 20’ of casing in at this time. 

8:00am- more casing was welded on here at MH A24-25 creek crossing. Crew will work to get this all tied in today. 

9:05am- carrier pipe is getting pulled and casing that was just welded on will need to be cut off and rewelded to get it straight and back on grade. 
Also at this time, Rip Rap is being delivered to E line crossing area for bank stabilization. 



10:30am- casing will have to be pulled due to a sag that has occurred over time. Crew will move onto next creek crossing at MH A18-19. 

11:20am- Crews are back here at MH A24-25 creek crossing to get casing right. Crew is trying to spin casing to get low spot up. Grouting will be done afterwards. 

12:40pm- pipe is spun and most of the dip is out of it. 

3:20pm- casing is spun a little more after a better means to rotate pipe was figured out. Grouting of casing will be at 7am tomorrow morning. 

4:05pm- crews have moved to MH A18-19 area to get the casing to grade on each end yet today. 

5:20pm- crew is rechecking grade on casing. Tomorrow we will rotate casing to get sag out of it. 