Turkey Creek Ph 1 - Flat Creek (Line Work)


7:30am- crew will be laying line again here at approximately STA 28+40. 

8:30am- 1st joint of the day now laid. Rock is having to be broke with hammer at this point. 

9:50am- 2nd joint is in with more rock to break. 

11:00am- 3rd joint now in place. 

11:55am- 4th joint placed. 

1:30pm- 5th joint in. 

2:40pm- 6th joint going in now. A lot of issues today with the laser. The heat is messing g with it. Both ends of the pipe get sealed off to restrict air flow between laying joints. 

3:10pm- 7th joint in place. 

4:00pm- joint 8 in as 9 gets placed. 

5:00pm- joint 10 is laid and backfilling is progressing. 

End of day-