6:55am- a look at the progress on the bore pit at the WWTF.
7:30am- Del-Sha has switched sides of the creek with their boring machine. Machine now setting on MH A16 side.
Flatcreek crew will be moving spoils from bore pit at MH A18 area and start moving pipe towards MH A7 area. No pipe will be laid today.
3:45pm- flatcreek has moved pipe, gravel and rock box to area of MH A7 to begin there in the morning.
Pump is at bore pit and currently recycling water...
They have also moved more spoil material to area of bank stabilization near MH A10.
4:10pm- Del-Sha has the 18” reamer through now and will begin with the 24” tomorrow here at the creek crossing at MH A16-17.
5:00pm- some grading is getting done near MH A11 area.