Thursday, July 16, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


6:40am- crews already working. Electrician working in disconnect box, and the discharge pipes will be installed today from pump stands up to pipes in wall. Pump stands are already mounted from yesterday’s work. 







2:10pm- Crew just called and they are headed offsite and will be back on Monday. Upright piping is installed now. 