Thursday, July 16, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:30am- crew will lay more pipe today. Clean up has also been occurring on up the line. 

8:30am- 1st joint for today laid. 

9:00am- 2nd joint in. 

9:30am- 3rd joint placed. 

10:00am- 4th joint in. 

10:30am- 5th now placed. 

11:00am- 6th piece now placed. 

11:35am- 7th laid. 

12:00pm- 8th joint laid. 

2:00pm- Joint 9 makes it in after more rock breaking. 

2:35pm-#10. 

3:10pm- 11th now placed. 

3:55pm- #12. 

4:40pm- 13 now placed. 

5:05pm- crew is calling it a day with 13 joints laid today. 