12:00pm- rock breaking has gone well today here at the bore pit ar the WWTF. There is a hydraulic hose mount issue now though so not much else will occur here today.
12:30pm- line crew has laid 14 joints so far today.
1:35am- joints 15&16 in with 17 getting set now.
2:40pm- 18&19 in with 20 getting placed.
3:30pm- Final joint for today as they are now at an encasement area. 22 joints or 308’ laid today of 27” ps46 pipe! Backfill will continue as part of the crew calls it a day.