7:00am- Iowa is in about 25’ so far. They had some issues yesterday with their equipment, but have ot resolved now.
7:30am- pump is getting set back up to pump water from pits so that grouting around casing can be done this morning.
8:25am- grouting of casing at MH A25 now occurring.
9:45am- more grout going in on MH A24 side now.
10:40am- the trench seal for MHA25 side of creek crossing is now done.
1:10pm-trench seal on MH A24 side is now completed.
2:00pm- pipes are now getting reinstalled into casing at creek crossing A24-25.
3:00pm-Heavy Rain has started and crew will button things up to call it a day.
No comments:
Post a Comment