Tuesday, July 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Iowa is in about 25’ so far. They had some issues yesterday with their equipment, but have ot resolved now. 

7:30am- pump is getting set back up to pump water from pits so that grouting around casing can be done this morning. 

8:25am- grouting of casing at MH A25 now occurring. 

9:45am- more grout going in on MH A24 side now. 

10:40am- the trench seal for MHA25 side of creek crossing is now done. 

1:10pm-trench seal on MH A24 side is now completed. 

2:00pm- pipes are now getting reinstalled into casing at creek crossing A24-25. 

3:00pm-Heavy Rain has started and crew will button things up to call it a day. 