6:45am- rock breaking occurring at the bore put at the WWTF.
7:40am- bore pit at MH A7 location has gained water overnight. Crew will bring 6” pump over and place it to get water down so that pipe can be laid today.
8:25am- 6” pump now operating to pump hole down.
10:50am- crew is now starting to dig as water is now pumped down.
11:30am- laser is back in bore RR02 and grade today is .690%; I believe it was originally reported as .730%.
12:00pm- tracer wire is now pushed through bore.
12:55pm- 1st joint for today tied to bore head towards MH A7.
1:45pm- 2nd in and 3rd joint going in.
2:45pm- 4th joint goes in and a 6’ piece will get them into the manhole. 60’ total from bore to manhole.
3:30pm- all pipe now connected to MH A7. Alignment to MH A8 will now occur.
Line is also lamped back to bore pit across tracks from MH A7.
4:20pm- 1 joint laid upstream of MH A7. Total of 74’ today. Crew will gravel up pipe and backfill to finish out the day.