Thursday, July 2, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:40am- Breaking rock in the Bore pit at WWTF is underway. Work started on this a couple days ago. 

7:30am- line crew digging for 1st joint this morning. 

7:50am- 1st joint of the day. 

8:20am- 2nd joint. 

8:45am- 3rd joint. 

9:20am- 4th joint. Pipe is off alignment slightly so an adjustment is being made over the next few pipes. 

9:45am- 5th pipe. 

10:15am- 6th. 

10:45am- 7th pipe. 

11:10am- 8 joints. 

11:35am- 9th. 

12:00pm- #10!

1:25pm- 11th now in place. 

1:45pm- 12th joint going in as new wire spool is added on. 

2:15pm- 13 in mow. 

2:40pm- 14th. 

3:05pm- 15th...

3:40pm- #16. 

4:10pm- last and final joint for today #17. Total footage today @ 238’. Backfill will consume rest of their day. 