Wednesday, July 29, 2020

Turkey Creek Ph 1 - Flat Creek(Line Work)


6:50am- Iowa has pulled bore machine and augers to attempt another steering maneuver. Its wanting to climb up, so they are trying to steer it back down. 31’ of casing is is at this time. 

7:50am- crew pumping water so that line across bore can be tied into manholes today here at A24-25. 

10:10am- pipe almost connected to casing and MH A24. 

10:30am- now connected and checked with level. 

10:45am- 6.25% slope across bore to MHA24. 



11:00am- boot is on between casing and pipe as gravel backfill occurs. 

1:20pm- seal at casing and pipe on MH A25 side is now being installed. 

2:00pm- jackhammer work occurs headed towards MH A25 from bore area. 

Heavy rain begins also and crew calls it a day again. 