Monday, July 6, 2020

Turkey Creek Ph 1- Flat Creek (Line Work)


7:00am- Line work will continue today as the crew approaches MH A18 area. 

Del-Sha will also begin with reaming the pilot hole today at creek crossing from MH A16-17. 

8:35am- 1st joint going in for today. 

9:05am- 2nd joint going in. 

10:15am- joints 3 & 4 now laid in place. 

11:45am- joint 5 makes it in after crew moved manhole 18 out of the spoil area and went down and put lid on MH A17 due to laser issues. 

1:30pm- #6 going in. 

2:10pm- Bore pit at WWTF is coming along slowly. 

Dirt pile is going to get moved so that power can be brought over to the main panel box site where conduit is sticking up. 

3:15pm- joints 7&8 are placed. 

3:40pm- 9th now placed. 

4:30pm- dug out for #10th joint, but not laying it so that backfill can be done. 