7:20am- crew is placing pumping to get pits ready for concrete today for the trench seals to be installed here on E line crossing.
8:20am- digging under casing to get the required clearance for concrete.
8:40am- Hose has blown on the excavator! Theres gonna be some down time.
10:15am- spacers are getting installed on pipes for creek crossing at MH A24-25 while they wIt on concrete.
10:55am- spacers are now on the pipe.
11:30am- concrete now onsite.
11:35am- west side on E line trench seal.
8yds of concrete applied on West side.
East side 24yds applied.
1:35pm- MH A27 is getting barrel section changed out due to a crack in it. They are also wrapping and strapping this today.
2:05pm- Done.
2:14pm- crew will set pump and pump water from pits at MH A24-25.
2:45pm- crew now loading casing with carrier pipe at creek crossing at MH A24-25.
3:55pm- carrier pipe is in, but it appears that the casing is short by 20’. Additional casing will be added.
4:15pm- crew will wrap things up here today, making necessary changes so casing can be added on.
4:45pm- concrete is poured at Head and tail walls for Bore Machine now.