Thursday, July 23, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:20am- crew is placing pumping to get pits ready for concrete today for the trench seals to be installed here on E line crossing. 

8:20am- digging under casing to get the required clearance for concrete. 

8:40am- Hose has blown on the excavator! Theres gonna be some down time. 

10:15am- spacers are getting installed on pipes for creek crossing at MH A24-25 while they wIt on concrete. 

10:55am- spacers are now on the pipe. 

11:30am- concrete now onsite. 

11:35am- west side on E line trench seal. 

8yds of concrete applied on West side. 

East side 24yds applied. 





1:35pm- MH A27 is getting barrel section changed out due to a crack in it. They are also wrapping and strapping this today. 



2:05pm- Done. 

2:14pm- crew will set pump and pump water from pits at MH A24-25. 

2:45pm- crew now loading casing with carrier pipe at creek crossing at MH A24-25. 

3:55pm- carrier pipe is in, but it appears that the casing is short by 20’. Additional casing will be added. 



4:15pm- crew will wrap things up here today, making necessary changes so casing can be added on. 

4:45pm- concrete is poured at Head and tail walls for Bore Machine now. 

















No comments:

Post a Comment