Monday, July 20, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- crew will begin laying pipe on up to MH A8 today. 

8:25am- laser issues this morning. Can’t get the dot to center back on target with grade. 

9:35am- 1st joint for today now laid. 

10:34am- 2nd joint in now. 

11:50am- 3rd and final joint for this run today due to the needed room for the bore pit here at MH A8 location. 

1:25pm- MH A7 is stacked on out and will finish being wrapped and strapped. 

2:40pm- MH A7 now finished and boot wrap is going on casing and pipe here at RR02. 

3:30pm- pipe is backfilled more on up to casing and equipment will begin getting moved back up line to E line stream crossing to begin work there tomorrow. 