Wednesday, July 22, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:40am- Iowa Trenchless will continue with getting the bore pit set up with the boring machine here at RR01. 

7:30am-crew here at E line crossing will get MH E1 set and tied to bore today. 

8:55am-1st & 2nd joints in now headed to MH E1 location. 

9:25am- joint 3 now in. 

10:10am- joint 4 is in as they dig out for MH E1 placement. 

10:40am- a 5th joint is laid to get on up to the manhole. Grading of gravel now for base to be set. 

11:45am- MH E1 base is set and connected to the pipe with an additional 6’ of 27” for a total of 76’ today so far. 

Lune is also lamped by laser back to MH A26. 



12:00pm- Grade is checked on manhole E1 and appears to be spot on. 

1:30pm- E1 is getting wrapped and strapped. 

Also at this time, surveying is out taking shots on casing. 

3:10pm- Del-Sha is having their machine worked on this afternoon. Should be back operational tomorrow. 



3:55pm- Iowa is closer to having things ready. Thrust block and head wall will be poured tomorrow respectively as shown in pictures. 















 