Crew will set manhole A 17 and begin here today laying pipe.
7:45am- shots are taken from bench mark for setting MH A17.
Also at this time Del-Sha has moved drill rig to this location for boring under creek.
10:00am- line crew has moved to hauling gravel, moving topsoil and switching out the 6” pump that has stopped working. Del-Sha continues to dig out at bore pit so that they can get started today at MH A17-16 location. Once the other 6” pump arrives the line crew will be back to set MH A17 and continue with laying pipe upstream of it.
12:45pm- crew back now to set MH A17. Grade is checked for depth. A little more will have to come out.
Bore pit area here at the creek crossing.
1:35pm- grading out gravel for MH A17 base.
2:05pm- base now set and manhole stacked for alignment to MH A18.
2:50pm- 1st joint of the day now getting placed.
3:30pm- 2nd joint now in place.
4:15pm- joints 3 & 4 now placed.
5:05pm- 5th and final for today.
Also Del- Sha has pilot hole through to the other side now.