Flatcreek to continue working on Line A and should reach MH A16 today. Del-Sha will get set up at next creek crossing @ MH A18-19.
8:40am- crew still digging out for 1st joint of pipe for today.
9:20am- joint 1 now in place.
9:55am- #2 now getting placed.
11:00am- 3rd pipe now in place.
11:35am- 4th pipe now in place as crew will begin to dig out for MH A16.
1:00pm- MH A16 area is dug out and crew will lay joint 5, then continue with setting 16’s base.
3:20pm- crew is stopping at this point due to Del-Sha wanting to bore this creek crossing next and they don't want the manhole in the way.
The crossing at here MH A18-19; Del-Sha says the rock isn’t solid enough for them to bore it directionally...?
4:20pm- line is backfilled now and pit dug on back for bore here at MH A16 location.
No comments:
Post a Comment