Tuesday, June 30, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Flatcreek to continue working on Line A and should reach MH A16 today. Del-Sha will get set up at next creek crossing @ MH A18-19. 
8:40am- crew still digging out for 1st joint of pipe for today. 

9:20am- joint 1 now in place. 

9:55am- #2 now getting placed. 
11:00am- 3rd pipe now in place. 

11:35am- 4th pipe now in place as crew will begin to dig out for MH A16. 

1:00pm- MH A16 area is dug out and crew will lay joint 5, then continue with setting 16’s base. 



3:20pm- crew is stopping at this point due to Del-Sha wanting to bore this creek crossing next and they don't want the manhole in the way. 

The crossing at here MH A18-19; Del-Sha says the rock isn’t solid enough for them to bore it directionally...?

4:20pm- line is backfilled now and pit dug on back for bore here at MH A16 location. 