Turkey Creek Ph 1 - Flat Creek (Line Work)


Grades to be shot on casing at Del-Sha’s site on stream crossing. More line will be laid near MH A14 by Flat Creek  and Iowa Trenchless will be back to continue boring at RR02. 
7:15am- water is getting pumped down at E line creek crossing so that grade can be shot on casing. 

9:00am- water pumped down and casing is lifted and is getting gravel and concrete placed under it on MH A26 side. 



10:30am- still placing concrete. 
10:55am- a little more rotation on the casing helps straighten casing. 



11:00am- joint #2 going in on A line. Rock breaking had to occur most of the morning so far. 

3:45pm- 3rd joint getting gravel now. 

4:20pm- 4th joint getting gravel.  

5:00pm- rock breaking occurs again. This will round out the day. 